VUDESK

¤Virtual University Of Pakistan Network¤



Welcome Visitors to VUDESK Family .Join VUDESK For Free to Get more Access to study material and lot of infotainment stuff. Stay Connected!!

VUDESk ALL Subject CODES
Find Your Subject Code , Join Group And You Will Get ALL related Data
ACC - Fundamentals of auditing and business
ACC311ACC501
ACF - (Accounting And Finance Related)
ACF619ACFI619
COM - (Commerce Related)
COM619COMI619
ECO - (Economics Related)
ECO401 ECO402 ECO403 ECO404
ENG - (English Related)
ENG001 ENG101 ENG201 ENG301 ENG401
ETH201 - Ethics (for Non-Muslims)
ETH201
ISL201 - Islamic Studies
ISL201
IT - (Info Tech Related
IT000IT0001IT430IT619ITI619
MIS - (Project And Internship Report)
MIS619 MISI619MIS620 MISI620
PAD - (Public Administration Related)
PAD619 PADI619
PAK301 - Pakistan Studies
PAK301PAK302
PHY - (Physics Related)
PHY101 PHY301
PSC201 - International Relations
PSC201PSC401
SOC - (Socialogy Related)
SOC101 SOC401
STA - (Statistics and Research)
STA301 STA630
URDU - (Urdu Related)
URD101

Discussion Question:

The project manager of XYZ Company asked a junior team member to develop a PERT Chart for a small project involving four activities – A, B, C and D – using the given relationship:

· Activity A and activity B are done simultaneously

· Activity C starts when activity A is finished

· Activity D starts only when both activities A and B are finished

The junior member worked on it and developed following PERT Chart:

 

Question: Analyze the PERT Chart and discuss, along with reasons, whether it was designed correctly or not.

Solution:

The above PERT chart is not correct.

At node 1, activity A is started and node 2, activity B is started.

According to condition 2, activity C starts only after A is finished. The PERT chart given is showing that activity C is starting only after A and B activities are finished.

………………………………

In my opinion PERT chart is not designed correctly, because the main reason is that, the purpose of this chart is about to achieve Goals on time, but in this chart no activity is getting complete on a single point.

2nd reason is that, if it said that activity A & B will complete, than C will be started, so C & D should remain the same to complete that process parallel, but in this chart D is taking much time to complete that tast




Tags: GDB, MGMT627, Management-current, Project, idea

Views: 6

*Member OF Week*

=======================

Popular Social Events

=======================

+ Member of the Day

+ Member of the Week

+ Member of the Month

+ Member of the Year

+ Miss VU

+ Mr VU

+ Gold Members

+ Vote for Miss VU

+ Vote for Mr VU

+ Members Points Table

+ Profile Points Allocation

+ Competition Corner

+ Our Fans Club

+ Certificate Winners

---------------------------------------

௵ Scholars Of Desk

 Gold Members

 MR VU,S

௵ MISS VU,S

 Members Of Month

 Team Members

 Moderators 

  ADMINS

ʭAdministrationʭ

Senior Admin : Yasmeen

VUDESK Owner : Ismail Shah

DMCA.com

VUDESK GROUPS

© 2013   Created by ʭIsmail Shahʭ.

Badges  |  Report an Issue  |  Terms of Service

-->