Q.
Let us assume that you are working as a Team lead in a renowned multinational company. The software project has 80 planned work tasks that are estimated to require 415 person-days to complete. At the time you have been asked to compute the Earned Value Analysis, 8 tasks have been completed. However, the project schedule indicates that 18 tasks should have been completed. The following scheduling data in person-days are available:
| Task |
Planned Effort |
Actual Effort |
| 1 |
3 |
3.5 |
| 2 |
4 |
5 |
| 3 |
5 |
5.5 |
| 4 |
4 |
3 |
| 5 |
6 |
7 |
| 6 |
7 |
6.5 |
| 7 |
5 |
5 |
| 8 |
7 |
7.5 |
| 9 |
8 |
|
| 10 |
8 |
|
| 11 |
3 |
|
| 12 |
2 |
|
| 13 |
14 |
|
| 14 |
2 |
|
| 15 |
7 |
|
| 16 |
6 |
|
| 17 |
8 |
|
| 18 |
7 |
|
Compute the following
1) SPI
2) Schedule variance
3) Percent scheduled for completion
4) Percent complete
5) CPI
6) Cost variance for the project.